The irrigation main line contractor and well motor installation companies have been going hard the past 8 days and now we are only days away from testing out the delivery system. The project has been going very well with everyone working together to complete the field work in a very short period of time and with little disruption to members.
|
The connection of the new main line from the well to the old existing system main line was made today Monday November 17th, 2014 |
This system will be temporary until the ponds are excavated and the new pump station installed by next spring.
|
The route of the new pipe through the west side of the practice area |
|
Magiorra Bros. installing the well motor and casing last Friday |
|
The well pump control unit and pressure tanks located at the back of the practice area Monday
|
By Thursday all the piping connections to the well will be made and a generator will be used to power the well motor for testing. It is expected that we will need to rely on this system until spring, which will necessitate more daytime watering.